Question: A project for a World Cup stadium is to be built with a very strict deadline schedule. The success criteria and their weights are as
A project for a World Cup stadium is to be built with a very strict deadline schedule. The “success criteria” and their weights are as follows:
CriteriaWeight Cost 20 Schedule 40 Safety 6 Environment 7 Change orders 5 Claim disputes 5 Relationship with other parties 5 Public image 8 Satisfied employees/workers 4 Total 100 The project finished with this information:
– There was a 2-day delay.
– There was a 1.4% budget overrun.
– One minor accident.
– No environmental pollution or violation.
– A few change orders and very few disputes.
– There was some tension between the owner and general contractor (GC) but in the end, everything was fine.
– The public image of the project was very positive.
– Many workers and employees complained about work conditions, but the GC management was able to resolve most of these complaints.
Using the provided Excel sheet, estimate the project success grade. Use the provided tables for grading cost and schedule, and your own educated opinion for other criteria.