Question: An individual assigned to a begin a project task April 2nd is unable to start until April 8th. When the project manager reschedules the task,

An individual assigned to a begin a project task April 2nd is unable to start until April 8th. When the project manager reschedules the task, what will she do before rescheduling the incomplete work? Select an answer: change the Actual Finish date to April 8th change the Actual Start to April 8th change the Status Date to April 8th change the Status Date to April 2nd

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!