Question: An industrial engineer is conducting a time study on a high-speed water cutting operation. With 60 cycles the average time per cycle was 12.60 minutes

An industrial engineer is conducting a time study

An industrial engineer is conducting a time study on a high-speed water cutting operation. With 60 cycles the average time per cycle was 12.60 minutes and the standard deviation was 1.45 minutes for a worker with a performance rating of 127 percent. Assume an allowance of 25 percent of the job. Calculate the following: A. What is the normal time for this job? B. What is the standard time for this job? Note: Extend answers four decimal places