Question: An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production

An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,200 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Design this layout using the decision rule of Longest Processing Time (LPT). What is the cycle time of this assembly line? a. 24 seconds b. 8 seconds Design this layout using the decision rule of Longest Processing Time (LPT). What is the cycle time of this assembly line? a. 24 seconds b. 8 seconds c. 124 seconds d. 36 seconds e. 80 seconds Click Save and Submit to save and submit. Click Save All Answers to save all answers