Question: An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production
An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,200 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza.
Task Immediate Predecessors Task Duration (Seconds)
A none 10
B A 14
C B 20
D B 16
E C,D 12
F E 2
Design this layout using the decision rule of Longest Processing Time (LPT). Which of the following is closest to the efficiency of your design?
| a. | 17% | |
| b. | 60% | |
| c. | 72% | |
| d. | 40% | |
| e. | 82% |