Question: An information on a project contains in a table below, each activity is labeled with A to J along with other information. Activity Predecessor Normal
An information on a project contains in a table below, each activity is labeled with A to J along with other information.
| Activity | Predecessor | Normal Time (Weeks) | Crash Time (Weeks) | Normal Cost ($) | Crash Cost ($) | Crash Cost Per Week ($) |
| A | - | 4 | 2 | 2000 | 3000 |
|
| B | A | 3 | 1 | 3000 | 4500 |
|
| C | A | 4 | 2 | 1000 | 2000 |
|
| D | A | 3 | 1 | 1400 | 3000 |
|
| E | B, C | 7 | 2 | 3000 | 6000 |
|
| F | G | 6 | 2 | 1200 | 3000 |
|
| G | D | 6 | 2 | 2000 | 3000 |
|
| H | E, F | 4 | 2 | 1500 | 2100 |
|
| I | F, H | 8 | 4 | 2400 | 4000 |
|
| J | E, I | 4 | 1 | 1300 | 1900 |
|
- Lengkapkan maklumat di dalam kolum jadual projek Crash Cost Per Week $.
Complete information in the tables column for the project Crash Cost Per Week $.
(6 markah/marks)
- Bina satu rajah rangkaian AON nod konfigurasi.
Construct a figure of AON node configuration network.
(9 markah/marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
