Question: An information on a project contains in a table below, each activity is labeled with A to J along with other information. Activity Predecessor Normal

An information on a project contains in a table below, each activity is labeled with A to J along with other information.

Activity

Predecessor

Normal Time

(Weeks)

Crash Time

(Weeks)

Normal Cost ($)

Crash Cost ($)

Crash Cost Per Week ($)

A

-

4

2

2000

3000

B

A

3

1

3000

4500

C

A

4

2

1000

2000

D

A

3

1

1400

3000

E

B, C

7

2

3000

6000

F

G

6

2

1200

3000

G

D

6

2

2000

3000

H

E, F

4

2

1500

2100

I

F, H

8

4

2400

4000

J

E, I

4

1

1300

1900

  1. Lengkapkan maklumat di dalam kolum jadual projek Crash Cost Per Week $.

Complete information in the tables column for the project Crash Cost Per Week $.

(6 markah/marks)

  1. Bina satu rajah rangkaian AON nod konfigurasi.

Construct a figure of AON node configuration network.

(9 markah/marks)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!