Question: An investor has a choice between two projects (Project A and Project B). Project A Project A requires the investment of $400,000 on 1 January

An investor has a choice between two projects (Project A and Project B).

Project A Project A requires the investment of $400,000 on 1 January 2020 and $200,000 on 1 April 2020. The project starts earning income from 1 July 2020. The income will be paid monthly in advance at an initial rate of $120,000 per annum. The income will decrease by $5,000 every year on 1 July and will cease at the end of 2030.

Project B Project B requires the investment of $600,000 on 1 January 2020. The project immediately starts earning income. The income will be received quarterly in arrears at an initial rate of $85,000. The income will increase at a compound rate of 4% per annum every four years with the first increase taking place on 1 January 2024 and will cease at the end of 2030.

(ii) Construct a quarterly cashflow schedule for Project B.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!