Question: An NEC 4 Engineering and Construction Contract main Option B is being used and the Client has not paid an amount due under the contract
An NEC Engineering and Construction Contract main Option B is being used and the Client has not paid an amount due under the contract and it is now fourteen weeks after the date which the Contractor should have been paid. Which TWO of the following procedures and amounts due would apply if the Contractor terminated its obligation to Provide the Works?Select TWO optionsA Pclause P and Pclause B Aclause and Aclause C Pclause and Pclause D Pclause and Pclause E Aclause A and Aclause