Question: An operator is tasked to operate two ( 2 ) machines instead of one ( 1 ) . 4 . 1 . 1 Use the

An operator is tasked to operate two (2) machines instead of one (1).
4.1.1 Use the given information to complete a multiple activity chart. (6)
Note: Load time =4 minutes
Unload time =2 minutes
Running time =6 minutes