Question: An operator needs 5 3 seconds to unload and load a machine, and 1 5 seconds to reach the next workstation. Each machine runs automatically
An operator needs seconds to unload and load a machine, and seconds to reach the next workstation. Each machine runs automatically for minutes and costs hour to run. Given a base part cost of and an operator rate of hour calculate:
a
How many machines should be assigned to an operator for lowest cost?
b
Calculate the production rate and visualise the result in a manmachine diagram.
c
The management wants a profit of on this product. Assuming no products are rejected during quality control, what should be the selling price of the product?
d
What is the utilization of the operator and the machines?