Question: An operator needs 5 3 seconds to unload and load a machine, and 1 5 seconds to reach the next workstation. Each machine runs automatically

An operator needs 53 seconds to unload and load a machine, and 15 seconds to reach the next workstation. Each machine runs automatically for 3.6 minutes and costs 25.8/hour to run. Given a base part cost of 1.68 and an operator rate of 33.5/hour, calculate:
a)
How many machines should be assigned to an operator for lowest cost?
b)
Calculate the production rate and visualise the result in a man-machine diagram.
c)
The management wants a profit of 10% on this product. Assuming no products are rejected during quality control, what should be the selling price of the product?
d)
What is the utilization of the operator and the machines?
 An operator needs 53 seconds to unload and load a machine,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!