Question: An order for 200 bolts is processed on work centers A and B. The setup and run times are as follows. It is decided to
An order for 200 bolts is processed on work centers A and B. The setup and run times are as follows. It is decided to overlap the lot on the two work centers and to split the lot into two lots. Please assume that the transfer lots are found using lot formulation. Move time between operations is 30 minutes. Work center B cannot be set up until the first lot arrives. Calculate the manufacturing lead time after overlapping and saving in manufacturing lead time. (If the answer is 10000 minutes 7 just enter 10000) Setup on A=50 minutes Run time on A=5 minutes per piece Setup on B=100 minutes Run time on B=7 minutes per piece
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts