Question: Analytics Exercise 4 - 2 ( Algo ) You work for a company that makes cell phones and have been made project manager for the
Analytics Exercise Algo
You work for a company that makes cell phones and have been made project manager for the design of a new cell phone. Your supervisors have already scoped the project, so you have a list showing the work breakdown structure, and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!
You have been given the information in Exhibit It Includes all the activitles required in the project and the duration of each activity. Also, dependencles between the activities have been identified. Remember that the preceding activity must be fully completed before work on the following activity can be started.
Your project is divided into five major subprojects. Subproject P Involves developing specifications for the new cell phone. Here, decisions related to such things as battery life, size of the phone, and features need to be made. These detalls are based on how a customer uses the cell phone. These user specifications are redefined in terms that have meaning to the subcontractors that will actually make the new cell phone in subproject S supplier specifications. These involve engineering detalls for how the product will perform.
The individual components that make up the product are the focus of subproject D Subproject "I" brings all the components together, and a working prototype is built and tested.
Finally, in subproject V suppliers are selected and contracts are negotlated.
Exhibit : Work Breakdown Structure and Activitles for the Cell Phone Design Project
tableMAJOR SUBPROJECTSACTIVITIESACTIVITY IDENTIFICATION,DEPENDENCY,DURATION WEEKSProduct Specifications PMarket research,Poverall product specifications,PPHardwarePPsoftwarePPSupplier specifications SHardwareSPsoftwareSPProduct design DBatteryDSDisplayDSCameraDSouter cover,DD D DProduct integration IHardwareIDUser interface,IDSoftware coding,IIPrototype testing,II ISubcontracting VSuppliers selection,VSSContract negotiation,V V
a Calculate the start and finlsh times for each activity. Leave no cells blank be certaln to enter wherever required. Answer is complete but not entirely correct.
b Determine the minimum number of weeks for completing the project.
Answer is complete but not entirely correct.
Minimum number of
weeks
c Find the activities that are on the critical path for completing the project in the shortest time.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock