Question: Analyzing a project schedule using CPM You are managing a construction project with the following tasks and dependencies: Task A: 5 days, no predecessor Task

Analyzing a project schedule using CPM
You are managing a construction project with the following tasks and dependencies:
Task A: 5 days, no predecessor
Task B: 8 days, must start after Task A.
Task C: 7 days, must start after Task A.
Task D: 4 days, must start after Task B.
Task E: 6 days, must start after Task C and Task D.
Use the data above, draw the project network diagram. Identify the critical path using Critical Path Method by calculating the earliest start and finish times, and the latest start and finish times. Determine the total project duration.
Make a diagram showing the critical path and the project duration.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!