Question: and answer the following. Problem 3 FA Project Management Review for Final Activity Immed Predec Optimistic Most Likehy Critical path? o B V w Y

and answer the following. Problem 3 FA Project
and answer the following. Problem 3 FA Project Management Review for Final Activity Immed Predec Optimistic Most Likehy Critical path? o B V w Y Z a m b 5 10 21 V 5 8 17 V 1 5 9 W.X 2 6 10 Y 3 8 19 Expected Completion Time Path Standard Deviation Which of the following is correctly stated with respect to the expected variance? The expected variance for W is 2. The expected variance for X is 4.78. The expected variance for Y is 1.78. The expected variance for Vis 50.55