Question: Ann's team is documenting activity attributes for each schedule activity. What attributes should be included? Select one: a . Activity ID , WBS ID ,
Ann's team is documenting activity attributes for each schedule activity. What attributes should be included?
Select one:
a
Activity ID WBS ID activity name, activity codes, activity description, predecessor and successor activities, logical relationships, and leads and lags
b Assumptions, cost estimates, responsibility assignment, and justification
c WBS code, resource requirements, and constraints
d Activity description, planned value, and estimate at completion
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock