Question: Ann's team is documenting activity attributes for each schedule activity. What attributes should be included? Select one: a . Activity ID , WBS ID ,

Ann's team is documenting activity attributes for each schedule activity. What attributes should be included?
Select one:
a.
Activity ID, WBS ID, activity name, activity codes, activity description, predecessor and successor activities, logical relationships, and leads and lags
b. Assumptions, cost estimates, responsibility assignment, and justification
c. WBS code, resource requirements, and constraints
d. Activity description, planned value, and estimate at completion