Question: Annual demand is constant 2 5 0 0 units per year, 2 5 0 working days and lead time averages 8 days with a standard

Annual demand is constant 2500 units per year, 250 working days and lead time averages 8 days with a standard deviation of 2 days, 95% does service require how much safety stock? (Z =1.64)
A)28 units
B)33 units
C)141 units
D)59 units