Question: Another approach is to develop the aggregate plan by simulating various master production schedules and calculating corresponding capacity requirements to see what? Vendors are satisfied
Another approach is to develop the aggregate plan by simulating various master production schedules and calculating corresponding capacity requirements to see what?
Vendors are satisfied with the plan.
Customers are satisfied with the plan.
If the resulting plan generates adequate profits.
If adequate labor and equipment exist at each workcenter.