Question: ans asap pls [20 points] A general contractor is working on a project with activities shown below: Activity 1 N 3 4 5 6 7
![ans asap pls [20 points] A general contractor is](https://dsd5zvtm8ll6.cloudfront.net/si.experts.images/questions/2024/12/6756b7d03e09f_3996756b7cfccff7.jpg)
ans asap pls
[20 points] A general contractor is working on a project with activities shown below: Activity 1 N 3 4 5 6 7 8 9 Predecessor- 1 1,2 1,2 3,4 4,5 5,7 6,8 Duration 3 8 1 5 6 7 5 1 6 Construct Critical Path Method (CPM) network for this project, compute the Early Start (ES), Early Finish (EF), Late Start (LS) and Late Finish (LF) dates, and identify the critical path(s)Step by Step Solution