Question: ANSWER 3.4.5 Given the following information: Most likely duration Predecessor a m b TE Var A 6 days none 3 6 9 B 6 days
ANSWER 3.4.5
Given the following information:
Most likely
duration Predecessor a m b TE Var
A 6 days none 3 6 9
B 6 days A 4 6 10
C 8 days A 2 8 8
D 4 days B 1 4 5
E 9 days B, C 3 9 15
F 4 days D 3 4 5
G 4 days E 1 4 7 H 8 days F,G 2 8 14
Complete the following TASK SENSITIVITY STEPS on the attached sheet
- Prepare WBS and Network Diagram
- Redo Task Times (Optimistic/ Most Likely/ Pessimistic),
- calculate TE and Variance
TE= (a+4m+b)/6 Variance= ((b-a)/6)2
- redo Network Diagram (with TE and Variance)
- Determine likelihood
- project will take longer than the critical path (use 36 days)
- project will take less than the critical path (use 31 days)
Z = ( D - u ) / a 2 where:
Z = Z score
D = desired time of the path in question
u = expected time along the path in question
the denominator is the square root of the sum of variances along the path in question
4. If you want to be XX% sure the project will be done within a certain amount of time (use 85%)
5. Calculate the likelihood that each non-critical path will take as long (or longer) than the critical path.
Step by Step Solution