Question: ANSWER 3.4.5 Given the following information: Most likely duration Predecessor a m b TE Var A 6 days none 3 6 9 B 6 days
ANSWER 3.4.5
Given the following information:
Most likely
duration Predecessor a m b TE Var
A 6 days none 3 6 9
B 6 days A 4 6 10
C 8 days A 2 8 8
D 4 days B 1 4 5
E 9 days B, C 3 9 15
F 4 days D 3 4 5
G 4 days E 1 4 7 H 8 days F,G 2 8 14
- Prepare WBS and Network Diagram
- Redo Task Times (Optimistic/ Most Likely/ Pessimistic),
- calculate TE and Variance TE= (a+4m+b)/6 Variance= ((b-a)/6)2
- redo Network Diagram (with TE and Variance)