Question: Answer. 400 units 2.15. The opening backlog is 800 units. Forecast demand is shown in the following. Calculate the weekly production for level production if

Answer. 400 units 2.15. The opening backlog is 800 units. Forecast demand is shown in the following. Calculate the weekly production for level production if the backlog is to be reduced to 100 units. Week 1 2 3 4 5 6 Total Forecast Demand 750 700 550 700 600 500 Planned Production 800 Projected Backlog Answer. Total production = 4500 units Weekly production = 750 units Backlog at end of week 1 = 800 units