Question: Answer above is incorrect, I need some help! Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the

Answer above is incorrect, I need some help!
Harris Fabrics computes its plantwide predetermined overhead rate annually on the basis of direct labor-hours. At the beginning of the year, it estimated that 29,000 direct labor-hours would be required for the period's estimated level of production. The company also estimated $523,000 of fixed manufacturing overhead cost for the coming period and variable manufacturing overhead of $2.00 per direct labor-hour. Harris's actual manufacturing overhead cost for the year was $636,742 and its actual total direct labor was 29,500 hours. Required: Compute the company's plantwide predetermined overhead rate for the year. (Round your answer to 2 decimal places.)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts