Question: Answer all correctly and I will 100% upvote!! QUESTION 1 If a planned receipt for an item is due in week 5 and the items
Answer all correctly and I will 100% upvote!!
QUESTION 1
If a planned receipt for an item is due in week 5 and the items lead time is 3 weeks, when will the corresponding planned order release occur?
Group of answer choices
Week 2
Week 5
Week 7
Week 3
Week 4
QUESTION 2
Engineering and process design information is critical to preparing which MRP input?
Group of answer choices
Periodic order quantity
Lead time
Bill of materials
Master schedule
Inventory records
QUESTION 3
Which of the following industries would probably Not utilize service resource planning?
Group of answer choices
Grocery stores
Airlines
Bicycle manufacturers
Hospitals
Restaurants
PreviousNext
QUESTION 4
If 60 units are on hand, the gross requirements for the next period are 120 units, and scheduled receipts for the next period is 200 units, what will the projected on-hand inventory level be at the end of the next period?
Group of answer choices
140
160
200
80
40
Question 5
Which of the following items is Not involved in developing an inventory record for a single item?
Group of answer choices
Bill of materials
Time bucket
Lot size
Lead time
Safety stock
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts