Question: Answer An overlapping network diagram is given below. What is the project duration? 6 5 LT = 5 D LT = 1 2 7 0
Answer

An overlapping network diagram is given below. What is the project duration? 6 5 LT = 5 D LT = 1 2 7 0 7 5 5 B E G A 3 4 8 5 5 5 C Select one: O a. 19 O b. 21 O c. 22 O d. 23