04 (40) Choose the closest answer a, b, c ord for the following questions A project manager performs Earned Value Analysis and finds the following results: EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000. What is right? A. EAC-400,000 B. EAC-550,000 C. BTC - 400,000 D. ETC - 75,000 Project costs are over budget when A. CPI1. C. CPI