Question: Answer any three questions (Including no. 4 , which contains 10 from 15 marks) 1. Classy project with one advantage. 2. What is project management?
Answer any three questions (Including no. 4 , which contains 10 from 15 marks) 1. Classy project with one advantage. 2. What is project management? 3. Illustrate some applications of LP in operations management. 4. A project has been defined to contain the following list of activities, along with their required times for completion: i. Calculate the expected time and the variance for each activity ii. Show the critical path. iii. What is the probability that the project can be completed in 36 weeks