Question: answer both 25. When planning time study for an operation, how should infrequent setup or restocking elements be handled? a. As a separate element b.

answer both
answer both 25. When planning time study for an
25. When planning time study for an operation, how should infrequent setup or restocking elements be handled? a. As a separate element b. As a variable allowance c. As a foreign element d. As an avoidable delay 26. Which of the following is an example of a foreign element? a. Worker has to take a break to use the bathroom b Worker dropped tool & bends to pick it up c. Worker answers quick question from supervisor d. Time study analyst drops watch and misses a reading