Question: use x=2 need correctly In a tool crib, workers come to take tools at (4+X) per hour on the average. Waiting for them costs Rs.

use x=2 need correctly use x=2 need correctly In a tool crib, workers

In a tool crib, workers come to take tools at (4+X) per hour on the average. Waiting for them costs Rs. (10+X) per hour. The service time per worker is in the tool crib is 12 minutes. What will be total waiting cost of the workers per day if it is 8 hours a day? Assume M/M/1 queuing system. X = last digit of your roll no