Question: Answer choices: B / C, B / B, E C, D / C / D F / Start / B F, B / B /

Answer choices: B / C, B / B, E C, D / C / D F /

Answer choices:

B / C, B / B, E C, D / C / D F / Start / B F, B / B / F D, G / G / D, F C / Start / D E / F / D

14 / 8 / 6 / 10

B, F, G / F, D, G / F, G

Consider the following AON network diagram. B 2 A 2 2 D E F 2 2 2 G 2 Complete the following table of activity sequencing. Activity Preceeded by [ Select [ Select ] > B [ Select] D [ Select] E [Select ] F [Select ] G [ Select ] If each activity takes 2 hours, what is the total project duration? [Select] Which activities have slack? [Select ]