Question: Answer Choices for question b. critical path drop-down menu are: 1. A-B-D-E-F 2. A-C-D-E-F 3. A-C-D-E-G 4. A-B-D-E-G The following information is known about a


Answer Choices for question b. critical path drop-down menu are:
1. A-B-D-E-F 2. A-C-D-E-F 3. A-C-D-E-G 4. A-B-D-E-G
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: a. Choose the correct network diagram for this project. O A. Start Finish Finish O C. Start Activity A B C D E F G Activity Time (days) 8 2 3 3 5 5 8 O B. O D. Immediate Predecessor(s) A A B. C D E E Start Start 9 D Finish Finish b. Determine the critical path and project duration. The critical path is path and the project duration is c. Calculate the slack for each activity. (Enter your responses as integers.) days. (Enter your response as an integer.) Slack Activity (days) A B D E F G