Question: c. Calculate the slack (days) for each activity. (Enter your responses as integers.) A: ___ B: ___ C: ___ D: ___ E: ___ F: ___


c. Calculate the slack (days) for each activity. (Enter your responses as integers.)
A: ___
B: ___
C: ___
D: ___
E: ___
F: ___
G: ___
The following information is known about a project to upgrade a point-of-sale system at Kids and Tots Apparel: Activity Immediate Predecessor(s) Activity Time (days) 8 A B A 3 A D 3 B, C D E 3 F 3 E G 5 E a. Choose the correct network diagram for this project. O A . e Start Finish Start Finish c. OD. Q > OD Start Finish Start Finish A-B-D-E-G A-C-D-E-G G 5 A-C-D-E-F b. Determine the critical A-B-D-E-F ation. The critical path is path and the project duration is days. (Enter your response as an integer.)Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock