Question: answer ((e)) question only and be clear pleaze Assume the WBS of a given project is illustrated in the following table: Activity A Predecessor Most
answer ((e)) question only and be clear pleaze
Assume the WBS of a given project is illustrated in the following table: Activity A Predecessor Most Likely 6 B D E F G Optimistic 4 4 6 4 2 5 2 Pessimistic 14 14 14 12 12 11 8 9 13 8 10 5 5 AB D CE E Non Find the mean and standard deviation of each task in this project then find the following: a) The project network. b) The critical path. c) The probability to finish the project in less than 35 weeks. d) The probability to finish the project in more than 31 weeks. e) The probability to finish the project between 31 and 35 weeks. f) The probability to finish the project in less than 31 or more than 35. g) In how many weeks can we complete the project with 90% probability
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
