Question: Answer Options (A): sometimes / always / never (C): required return / IRR / MIRR (D) NPV method / IRR method If an independent project

 Answer Options (A): sometimes / always / never (C): required return

Answer Options

(A): sometimes / always / never

(C): required return / IRR / MIRR

(D) NPV method / IRR method

If an independent project with conventional, or normal, cash flows is being analyzed, the net present value (NPV) and internal rate of return (IRR) methods agree. Projects W and X are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. NPV (Dollars) Year Project W Project X 800 $1,000 -$1,500 $350 $500 $600 $750 $200 $350 $400 $600 600 Project X 400 4 Project W 200 If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and IRR methods agree or conflict? -200 O The methods agree 0 2 46 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) The methods conflict A key to resolving this conflict is the assumed reinvestment rate. The IRR calculation assumes that intermediate cash flows are reinvested at the that the rate at which cash flows can be reinvested is the , and the NPV calculation implicitly assumes As a result, when evaluating mutually exclusive projects, the is usually the better decision criterion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!