Question: answer part B please Cost overruns A. Three months into a lump sum project, this project manager has realized that his company is overrunning costs
answer part B please
Cost overruns
A. Three months into a lump sum project, this project manager has realized that his
company is overrunning costs on half of the direct work activities. They are
under-running on the other half. The bottom line looks okay, maybe even on the plus
side. Is this possible? Can he do anything about the codes that are overrunning? Since
the bottom line looks okay, should he even worry about it? This projects superintendent
does not want to report any single line item cost overruns to the home office, and asks
the PM to forecast the original estimate in each case so that the variances zero out. How
can the PM cover up this situation? What are the ramifications if he does what the
superintendent is asking? As long as the project makes the original fee, does it really
matter how individual cost codes turn out?
B. This is a similar situation to the above, except all of the codes appear to be overrunningtheir estimates. The project looks like it is going in the tank to a tune of approximately $500,000.
What are some of the reasons this overrun could be occurring?
Should the project manager and the superintendent just hold on and ride it out? What are some potential resolutions you could recommend to the jobsite team?
Should they ask for assistance from the home office?
Should they start looking for a new employer?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock