Question: Three months into a lump sum project, this project manager has realized that his company is overrunning costs on half of the direct work activities.
Three months into a lump sum project, this project manager has realized that his company is overrunning costs on half of the direct work activities. They are under-running on the other half. The bottom line looks okay, maybe even on the plus side. Is this possible? Can he do anything about the codes that are overrunning? Since the bottom line looks okay, should he even worry about it?
This projects superintendent does not want to report any single line item cost overruns to the home office and asks the PM to forecast the original estimate in each case so that the variances zero out.
How can the PM cover up this situation? What are the ramifications if he does what the superintendent is asking? As long as the project makes the original fee, does it really matter how individual cost codes turn out?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
