Question: Answer Question 16 and 17 A regional infrastructure building and maintenance contractor must decide to buy a new compact horizontal directional drilling (HDD) machine now,


Answer Question 16 and 17 A regional infrastructure building and maintenance contractor must decide to buy a new compact horizontal directional drilling (HDD) machine now, or wait andbuy it 2 years from now when a large pipeline contract will require the new equipment. The HDD machine will include an innovative pipeloader design and amaneuverable undercarriage system. The cost of the system is $70,800 if purchased now or an estimated $80,100 if purchased 2 years from now. 16. At i = 12% per year and f= 3% per year, determine if the contractor should buy now or later without any adjustment for inflation. 17. At i = 12% per year and f= 3% per year, determine if the contractor should buy now or later with inflation considered
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts