Question: Answer questions 1 - 2 based on the following information: The project described in the following table has just begun. Use the critical path method
Answer questions based on the following information:
The project described in the following table has just begun. Use the critical path method CPM to determine the slack time for each of the project activities presented below
png
Question
pts
What is the earliest finishing time EF for activity H
IncorrectQuestion
pts
Given that all other activities will be completed on time, what is the allowable slack time in weeks for activity D Please type the number only eg if your answer is weeks, then type
Questions are based on the information below.
The project described in the following table has just begun.
png
Question
pts
What is the expected completion time? Please type the number only eg if your answer is weeks, then type
Question
pts
What is the path mean for path ABF
Question
pts
The project is scheduled to be completed in weeks. What is the probability for the project shown in question above being late for more than week? Keep four decimals in all intermediate steps eg a probability can be in terms of or and keep two decimals for your final solution eg if a final solution probability is then round it to
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock