Question: Answer questions 1 - 2 based on the following information: The project described in the following table has just begun. Use the critical path method

Answer questions 1-2 based on the following information:
The project described in the following table has just begun. Use the critical path method (CPM) to determine the slack time for each of the project activities (presented below).
1.png
Question 1
1/1 pts
What is the earliest finishing time (EF) for activity H (2-8)?
8
14
3
11
IncorrectQuestion 2
0/1 pts
Given that all other activities will be completed on time, what is the allowable slack time (in weeks) for activity D? Please type the number only (e.g., if your answer is 10 weeks, then type 10).
5
Questions 3-5 are based on the information below.
The project described in the following table has just begun.
2.png
Question 3
1/1 pts
What is the expected completion time? Please type the number only (e.g., if your answer is 10 weeks, then type 10).
13
Question 4
1/1 pts
What is the path mean for path A-B-F?
3
10
5
Question 5
1/1 pts
The project is scheduled to be completed in 15 weeks. What is the probability for the project (shown in question 3 above) being late for more than 1 week? Keep four decimals in all intermediate steps (e.g., a probability can be in terms of 0.3333 or 33.33%) and keep two decimals for your final solution (e.g., if a final solution probability is 0.33333, then round it to 33%).
71%
29%
18%
82%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!