Question: Answer questions 15-16 based on the following information. We would like to use the critical path method (CPM) to determine the duration of the following

Answer questions 15-16 based on the following information.

We would like to use the critical path method (CPM) to determine the duration of the following project. Assume we start this project at time zero.

Activity

Expected Processing Time (in Weeks)

a (1-2)

5

b (2-3)

6

c (4-5)

5

d (2-5)

2

e (5-6)

5

How many weeks do we need to complete this project (that is, what is the duration of the entire project)?

None of the answers is correct

10

11

12

Assume no other activities are delayed. What is the maximum slack time for activity c (4-5)

0

1

5

3

2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!