Question: Answer questions 15-16 based on the following information. We would like to use the critical path method (CPM) to determine the duration of the following
Answer questions 15-16 based on the following information.
We would like to use the critical path method (CPM) to determine the duration of the following project. Assume we start this project at time zero.
| Activity | Expected Processing Time (in Weeks) |
| a (1-2) | 5 |
| b (2-3) | 6 |
| c (4-5) | 5 |
| d (2-5) | 2 |
| e (5-6) | 5 |
How many weeks do we need to complete this project (that is, what is the duration of the entire project)?
None of the answers is correct
10
11
12
Assume no other activities are delayed. What is the maximum slack time for activity c (4-5)
0
1
5
3
2