Question: Answer questions 2 - 5 based on the information provided in Table 1 . You are given a project that consists of 8 activities. For
Answer questions based on the information provided in Table You are given a project that consists of activities. For each activity, you know the activity duration and its immediate predecessor. Additionally, for the purpose of project crashing, you are also given the cost to expedite each activity per day and the maximum number of days that you can expedite an activity.
Which of the following isare the critical paths:
ABCGH
ABDFH
ABEFH
ABCDEFGH