Question: Answer Questions 34 through 37 based on the following project: If task B is delayed by 3 wks, what is the impact to the project?

 Answer Questions 34 through 37 based on the following project: If

Answer Questions 34 through 37 based on the following project: If task B is delayed by 3 wks, what is the impact to the project? The project duration will increase by 3 weeks The project duration will not increase The project duration will increase by 2 weeks The early start for task E will increase by 3 weeks but the project duration wil not increase None of the above