Question: Answer questions 7 - 8 based on the following diagram. Q: You are given a line balancing problem for a product with the following diagram,

Answer questions 7-8 based on the following diagram.
Q: You are given a line balancing problem for a product with the following diagram, what are the immediate predecessors of task 5?
Q7 pic-1.png
Group of answer choices
2,3,4
3,4,5
3
2
Flag question: Question 8
Question 82 pts
If the demand for this product is 10, and the maximum production time is 70 hrs. What is the theoretical minimum number of workstations, and what is the line efficiency by using the ranked positional weight heuristic? (Assume the time given in the diagram has units of hours)
Group of answer choices
4,0.833
3,0.953
3,0.714
4,0.714

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!