Question: Answer the following questions using the data provided in the table below that describes project planning information for a network diagram. activity activity time immediate
Answer the following questions using the data provided in the table below that describes project planning information for a network diagram.
| activity | activity time | immediate process |
| a | 7 | - |
| b | 1 | a |
| c | 4 | a |
| d | 5 | b,c |
| e | 4 | d |
| f | 5 | e |
| g | 8 | e |
A. What is the Critical Path?
B. What is the project completion time?
C. What is the slack time on activity C?
D. What is the slack time on activity F?