Question: Answer the following questions using the data provided in the table below that describes project planning information for a network diagram. activity activity time immediate

Answer the following questions using the data provided in the table below that describes project planning information for a network diagram.

activity activity time immediate process
a 7 -
b 1 a
c 4 a
d 5 b,c
e 4 d
f 5 e
g 8 e

A. What is the Critical Path?

B. What is the project completion time?

C. What is the slack time on activity C?

D. What is the slack time on activity F?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!