Question: Answer the following questions using the network diagram. table [ [ Activity , table [ [ Immediate ] , [ Predecessor ] ]
Answer the following questions using the network diagram.
tableActivitytableImmediatePredecessorActivity timeANone,BNone,CBDA CEBFDGE
a Calculate the Forward and Backward passes of each activity.
b Determine the Critical Path of the Project.
c Determine the Project Completion Time.
d Calculate the Slack value of each activity.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock