Question: Answer the hext seven questions using the information below: The following table represents the activities of a project, their relationships, and their pessimistic, most likely,

Answer the hext seven questions using the information below:
The following table represents the activities of a project, their relationships, and their pessimistic, most likely, and optimistic times (in days):
\table[[Activity,\table[[Immediate],[predecessor(s)]],Optimistic,\table[[Most],[likely]],Pessimistic],[A,-,2,3,4],[B,-,3,4,11],[C,A, B,2,4,6],[D,B,1,8,9],[E,E,1,2,3]]
Question 53(3 points)
Saved
(3 points) What is the earliest finish time of activity C?