Question: Answer the next 3 Questions based on the following table from a process analysis (minutes/job) (jobs/ hr) Resource # of resource units Unit load Unit

Answer the next 3 Questions based on the following table from a process analysis

(minutes/job)

(jobs/hr)

Resource

# of resource

units

Unit load

Unit

capacity

Plastic

3

5.7

10.53

Metal

4

9.4

6.38

Copper

3

7.8

7.69

1. What is the process capacity (in jobs/hr)?
a. Capacity < 20
b. 20 Capacity < 25
c. 25 Capacity < 30
d. Capacity 30 17.
2. Adding another unit of Metal will increase process capacity.
a. True
b. False
3. Increasing the bottleneck resource units by 1 will increase process capacity (in jobs/hr) to:
a. Capacity < 20
b. 20 Capacity < 25
c. 25 Capacity < 30
d. Capacity 30

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!