Question: Answer the next three questions using the following information. A quality analyst wants to construct a sample mean chart for controlling a packaging process. He

Answer the next three questions using the following information. A quality analyst wants to construct a sample mean chart for controlling a packaging process. He knows from past experience that the process standard deviation is two ounces. Each day last week, he randomly selected four packages and weighed each. The data appears below. What is the overall sample mean?

Question 9 options:

23.1

21.0

20.6

19.2

20.0

Question 10 (1 point)

What is the lower 2-sigma x-bar chart control limit?

Question 10 options:

20.5

18.9

22.6

18.6

2-sigma

Question 11 (1 point)

Based on the x-bar chart, the above process is in control.

Question 11 options:

TRUE

FALSE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!