Question: Answer the questions about c language I have started a craft sewing business. Every hour, I produce one sock, which takes 10 minutes; one sweatshirt,
Answer the questions about c language
I have started a craft sewing business. Every hour, I produce one sock, which takes 10 minutes; one sweatshirt, which takes 30 minutes; and one t-shirt, which takes 20 minutes. What is the mean turnaround time to produce an item, per item, in minutes? What is the throughput, in terms of items produced in an eight-hour shift
Step by Step Solution
There are 3 Steps involved in it