Question: Answer the questions below. Show work, as needed. There is a project with the following requirements: Task Duration (in days) Dependency A 10 B 12

Answer the questions below. Show work, as needed.

  1. There is a project with the following requirements:
Task Duration (in days) Dependency
A 10
B 12
C 15 A
D 7 B
E 8 C & D
F 11 E
G 4 E

  1. Draw the diagram to denote the total project schedule (this can be done on paper and copy and paste the image in this word document or any other tool).
  2. Answer the following questions:
  • What path is the critical path?
  • How many other paths are there? Note them.
  • What is the float/ slack in the schedule?
  • What is the early start, late start, early finish, and late finish of the project? (Note: format your answer based on the videos from this week)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!