Question: Answer the questions below. Show work, as needed. There is a project with the following requirements: Task Duration (in days) Dependency A 10 B 12
Answer the questions below. Show work, as needed.
- There is a project with the following requirements:
| Task | Duration (in days) | Dependency |
| A | 10 | |
| B | 12 | |
| C | 15 | A |
| D | 7 | B |
| E | 8 | C & D |
| F | 11 | E |
| G | 4 | E |
- Draw the diagram to denote the total project schedule (this can be done on paper and copy and paste the image in this word document or any other tool).
- Answer the following questions:
- What path is the critical path?
- How many other paths are there? Note them.
- What is the float/ slack in the schedule?
- What is the early start, late start, early finish, and late finish of the project? (Note: format your answer based on the videos from this week)
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock