Question: answer the second question. The first one is a reference to check your answer using the work. answer this one below V A Company is
answer the second question. The first one is a reference to check your answer using the work. 
answer this one below V

A Company is planning a new product line and a new factory to produce the parts. The product line will include 8 different models, and annual production of each model is expected to be 821 units. Each product will be assembled of 281 components, but 37% of these will be purchased parts (not made in the new factory). There are an average of 8 processing operations required to produce each component, and each processing step takes 54sec (including an allowance for setup time and part handling). The factory will operate one shift, 289 days a year. All processing operations are performed at work cells that include a production machine and a human worker. How many workers are needed